LOCATION:   Immingham, Humber

SECTOR:          Port

PERIOD:           10 Days

| ABP GRESLEY WAY, IMMINGHAM

CIVIL ENGINEERING     |     DRAINAGE     |     GROUNDWORKS     |     CONCRETE WORKS

A business located next to the road was suffering from water damage due to the condition of the road and the volume of HGV s using it during flooded periods. Our client wanted to correct the problem and prevent further disruption for the business owner.

CONTACT US

CALL OUR TEAM ON 0800 230 0215

| OBJECTIVE

 

Create positive drainage by installing the necessary pipework, gullies, and manholes, leaving provision to extend the drainage system if required in the future. All work was to be carried out within a three-week period.

 

 

| DELIVERY

 

NMC Surfacing erected two-way lights with lighting and guarding to manage the traffic. Water filled barriers were used to create a safe working environment for the workforce.

 

To create the positive drainage, it was necessary to track and install a pipe from an existing manhole located adjacent to the site, to the point of the access road where the new gullie run would begin. Once this had been completed it allowed us to construct the first manhole chamber. A mini digger was used to excavate trenches either side of the manhole and a plastic twin wall piping was installed to create gully’s. The trench work was 1m deep and provided a fall allowing surface water to drain away. A depth of 100mm was left for the reinstatement of the asphalt, and this was all hand-laid.

| Scotland

 

20-23 Woodside Place,

Glasgow, G3 7QF

 

0141 5821288

| South-West

 

Lower Castle Street,

Bristol, BS1 3AG

 

0117 3131517

OUR LOCATIONS

| London

 

85 Tottenham Court Rd,

London, W1T 4DU

 

0207 2683077

| Central

 

3 Ebor Court,

Doncaster, DN6 7FE

 

01302 275122

| South-East

 

11 Gateway 1000,

Stevenage, SG1 2FP

 

01438 742122