Our client required a full refurbishment of their car park, including surfacing, civils, and landscaping works. This project had to be carried out during the day due to EA restrictions. The store is a live site situated in a busy town centre, minimal disruption to the local community and trading hours was essential.

Services Delivered: Surfacing | Civil Engineering | Line Marking | Hard Landscaping


The project required a complete refurbishment of the car park, including 1,200m2 of resurfacing to parking bays, walkways, and carriageways. All road markings had to be altered to reflect the new layout and required the relocation of signs and lamp columns. Civils works included the installation of block paving, kerbs, aco channels, bollards, and man holes. We were also instructed to carry out landscaping works which included the siting of timber knee boards, plants, and bushes.


The project was very challenging given the restraints of the location and working hours available. We requested permission allowing us to carry out some of the work on Sunday nights minimising disruption to the store and surrounding roads. Traffic Management was required throughout the project and all working areas had to be Heras fenced off.

We were required to adhere to the Asda working practice at all times. Communication with the Store Manager was paramount to ensuring the project ran smoothly and was completed on time.