The client had identified areas of the car park that had fallen into disrepair. The car park belonged to a busy retail park and consideration needed to be given to the effect any disruption may have on trade.

Services Delivered: Surfacing | Line Marking


The job required the planning out and resurfacing of two areas on the car park that had become worn. This project needed to be completed outside of normal trading hours to limit disruption to the retailers and members of the public.


It was agreed that the work would take place during the hours of 21:00 - 04:00 and would be phased over two nights. Each phase included the planning out and resurfacing of an area ensuring that there would be no impact during the day.

Traffic Management was still required as there was a 24-hour fast food outlet on the retail park. NMC Surfacing provided two traffic marshals, signage and barriers, and kept the outlet manager aware of their progress throughout the project.

A total of 1,735m2 was excavated. The planed areas were sprayed with tack coat and resurfaced and all joints were over banded before the lining was refreshed.